Frazier excels at challenging projects
| 12 Jul 2010 |
Frazier is proud to provide concrete paving services for the Timpanogos Plant Expansion project in American Fork, UT. Frazier’s Concrete Division completed the 130,000 SF concrete paving job in 4 consecutive days placing over 3600 yards in 900 yard increments. Frazier provides on time, high quality work every time, even on the most demanding and challenging of projects. For the latest Timpanogos project images click here. |
|
 |
Frazier helped us complete the project ahead of schedule (...) and was instrumental in helping us obtain an Outstanding Final Evaluation for the project. This was a job well done. We look forward to working with Frazier Masonry on future projects.

- Dan Billings - Project Manager - Straub Construction, Inc.
|
|
|