Frazier Tops out P-206/P-028 BEQ & Dining Facility Project27 Mar 2009

Frazier Completes work on P-206/P-028 BEQ & Dining Facility in Camp Pendleton, CA. View the Project Gallery here.


Golden Valley High School
Santa Clarita, CA
Frazier Masonry crews completed 24 CMU buildings in six and half months as part of a Soltek Pacific design build project. Frazier Masonry overcame sand storms, extreme winds and even a blanket of snow. Transportation challenges, lack of onsite water reserves and no utilities did not stop production. [They] exceeded expectations by completing the project 17 days ahead of the baseline schedule. As a Project Superintendent I look forward to working with Frazier Masonry in the future.
--Joe Whipple - Project Superintendent - Soltek Pacific Construction


About FMC    |    Services    |    Contact Us    |    Employment    |    Admin
Copyright © 2009 Frazier Masonry Corporation. All rights reserved.